The GMAT Sample Math question for the day is from the topic Work and Time.
Question 2
A can complete a project in 20 days and B can complete the same project in 30 days. If A and B start working on the project together and A quits 10 days before the project is completed, in how many days will the project be completed?
  1. 18 days
  2. 27 days
  3. 26.67 days
  4. 16 days
  5. 12 days
The correct choice is (A) and the correct answer is 18 days.

Explanatory Answer
If A can do complete a project in 20 days, then A will complete 1/20th of the project in a day.
Similarly, B will complete 1/30th of the project in a day.

Let the total number of days taken to complete the project be x days.

Then, B would have worked for all x days, while A would have worked for (x - 10) days.

Therefore, A would have completed (x-10)/20th of the project and B would have complete x/30 th of the project.

i.e., (x-10)/20 + x/30 = 1

Solving for x, we get x = 18.

 


Add to del.icio.us Add to del.icio.us Stumble It Stumble It digg this digg this
Copyright 2004-10 4GMAT.COM
Test Catalyst (India) Private Limited
All rights reserved
GMAT™ and GMAC™ are registered trademarks of the Graduate Management Admission Council™. The Graduate Management Admission Council™ does not endorse, nor is it affiliated in any way with the owner or any content of this web site.