4GMAT - GMAT Online Practice Test
topic wise list of questions  Topicwise List of Questions
GMAT Prep
GMAT Class @ Chennai, Mumbai, Bangalore
GMAT Classes in India Intensive classes for GMAT in Madras, Bombay and Bangalore in India. Weekend & Weekday classes. Includes study material and tests. Tutors include 98%ilers in GMAT & ISB / IIM Graduates.
gmat math
GMAT Prep
Other useful links
Testimonials
GMAT Prep Freebies
Contact 4GMAT
Chennai : 95000 48484
Mumbai : 80970 48484
Bangalore : 91419 48484
Follow 4GMAT on Facebook    Follow 4GMAT on Twitter    GMAT Prep Blogs by 4GMAT    GMAT Prep Videos by 4GMAT     Google+   Follow 4GMAT on LinkedIn
gmat practice test
You are here: Home » GMAT Test Prep Questions » Work Time & Pipes Cisterns » Question 1
Linear Equations   GMAT Math Practice - Work Time
The question given below is a problem solving question in Work and Time.
Question 1
Working together, Jose and Jane can complete an assigned task in 20 days. However, if Jose worked alone and complete half the work and then Jane takes over the task and completes the second half of the task, the task will be completed in 45 days. How long will Jose take to complete the task if he worked alone? Assume that Jane is more efficient than Jose.
  1. 25 days
  2. 30 days
  3. 60 days
  4. 65 days
  5. 36 days
The correct choice is (C) and the correct answer is 60 days.

Explanatory Answer
Let us assume that Jose will take x days to complete the task if he works alone and that Jane will take y days to complete the task if she worked alone.

From the information provided in the first statement of the question, we know that they will complete the task in 20 days, if they worked together on the task.
Therefore,1/x + 1/y = 1/20
From the second statement, we can conclude that x/2 + y/2 = 45
Or, x + y = 90 => x = 90 - y.

Substituting the value of x as 90 - y in the first equation, we get 1/(90-x) + 1/y = 1/20
Or y2 - 90 + 1800 = 0.
Factorizing and solving for y, we get y = 60 or y = 30.

If y = 60, then x = 90 - y = 90 - 60 = 30 and
If y = 30, then x = 90 - y = 90 - 30 = 60.

As the question clearly states that Jane is more efficient than Jose, the second answer is the only possible alternative.

Hence, Jose will take 60 days to complete the task if he worked alone and Jane will take only 30 days to complete the same task.

 


Add to del.icio.us Add to del.icio.us Stumble It Stumble It digg this digg this
Copyright 2004-13 4GMAT.COM
Test Catalyst (India) Private Limited
All rights reserved
GMAT™ and GMAC™ are registered trademarks of the Graduate Management Admission Council™. The Graduate Management Admission Council™ does not endorse, nor is it affiliated in any way with the owner or any content of this web site.